Construction Timeline:
2004 – A Capital Asset Realignment for Enhances Services (CARES) Commission recommends the construction of a new VAMC in Louisville
June 2006 – VA announces that a replacement hospital will be built
September 2008 – Funding approved for new hospital
May 11, 2011 – Public meeting held to discuss the five site options
June 29, 2012 – 34-acre site off of Brownsboro Rd. is selected as the new hospital location
March 2018 – Lawsuit filed to challenge the selection of the Brownsboro Rd. site
March 18, 2021 – Lawsuit dismissed
August 17, 2021 – $840 construction contract awarded to Walsh-Turner Joint Venture
November 11, 2021 – Groundbreaking Ceremony held on Veteran’s Day. Construction begins
October 2022 - All construction options are exercised ($68 Million)
Early 2026 – Construction complete